Reduce Downtime with Smart Scheduling
By taking
a few extra administrative steps, maintenance managers
can implement more preventive maintenance in less time.
By Leland Parker, DPSI Senior
Consultant
For years, maintenance managers
have successfully been using enterprise asset management
(EAM) or computerized maintenance management system
(CMMS) software to decrease unscheduled downtime. But
managers whose plants are running at maximum capacity
face the classic struggle between maintenance and
production. One department needs to idle the equipment
for preventive maintenance (PM) to avoid unscheduled
downtime while the other must have unbroken uptime to
meet its production quota cost.
Maintenance managers can help ease
this tug of war by implementing a straightforward
approach called Smart Scheduling. Smart Scheduling can
reduce planned downtime by as much as 50 percent, making
it easier to wedge maintenance into a busy schedule and
provide efficiencies that lead to documented cost
savings.
Coordinate
Activities
Smart Scheduling means coordinating
all PM activities for related assets, then using an
EAM’s scheduling capabilities to plan ahead and “gang
up” maintenance events,
ensuring that all necessary resources and materials are
available for the time that the equipment is scheduled
to be out of service. This will maximize efficiency and
minimize downtime. Most EAM software packages can help
do this, but some newer programs have features to
simplify the process.
For example, in two days a plant is
scheduled to complete an annual PM activity on machine
A, a key piece of equipment. To complete the PM
activity, related equipment
must be taken down, including machines B and C for an
hour or so, which probably will upset the production
manager.
To lessen the blow, the EAM can be
used to look a month or two into the future to see if
there are any additional PM activities coming up for
machines A, B, and C. As it
turns out, B and C are due for a monthly PM activity
next week, and a semi-annual activity is scheduled for A
the following week. Now all four can be done at the same
time, minimizing downtime, increasing efficiency, and
reducing costs. Or if machine C has a yearly PM activity
coming up in two weeks, as long as it is down for the
monthly, the yearly can be done at the same time.
Implementing the Program
Reaping the benefits of Smart
Scheduling can require some extra planning and
decision-making. Following are a few highlights of some
of the steps involved in
implementing a Smart Scheduling program.
Identify common procedures and
tasks. Begin the process by fully identifying common
procedures, making sure to include all estimated parts,
labor, and tools. List labor
by craft; determine the PM schedule. Start by reviewing
the manufacturer’s recommendations then temper that with
experience.
For example, if an uncommon number
of breakdowns occur between scheduled maintenance
events, plan to schedule events more frequently.
Conversely, if following the manufacturer’s
recommendations leads to unnecessary maintenance, adjust
the frequency based on the experience with the
facility’s operating environment.
Write tasks and procedures to cover
the required PM. To make sure all the exact resources
required to do one particular job are available,
duplicate or copy the procedure using those functions in
the EAM software. Change items that may not be
applicable to the equipment being serviced. With these
changes, the procedure is unique to that piece of
equipment but the procedure/task list is kept consistent
and concise.
If the duplicate and copy links
functions are not available in the EAM package, write a
generic procedure that can be used repeatedly. Remember
to make the tasks applicable to all similar equipment
and customize procedures by calling out the appropriate
tasks, parts, tools, and craft labor.
Determine
a Scheduling Method
The scheduling function of most
software programs gives three choices: “since last
completed,” “since last scheduled,” and a metered system
based on equipment run time or a calendar.
With the “since last completed”
option, if the PM activity is originally scheduled on
May 7 but is not completed until May 30, the PM will
adjust the schedule to set the next due date on April
30. This can increase efficiency because things are
being done only as needed.
Over time, the “since last
completed” approach yields an advantage, as it will
distribute workloads and schedule tasks based on
documented evidence of what you can accomplish in one
given period.
The “since last completed” option
also has its disadvantages, depending on the EAM
software. Older EAM systems usually do not ensure that
monthly, quarterly, semiannual, and annual PM activities
come due at the same time. If the monthly activity is
done but not the quarterly, it is possible to throw the
entire system off track and lose any coordination that
may have been established between maintenance
activities.
“Since last scheduled” means that
the activity is done every 30 days on the seventh of the
month, for example. One benefit is that a paper trail is
maintained. This method will ensure schedule
documentation. But a bigger advantage is that this
method will maintain the synchronization between
maintenance activities that have varying frequency.
There is also a downside. If a
monthly PM activity is scheduled for today but does not
get completed until the end of the month, the EAM system
will prompt to do it again
one week later, which is not necessary.
Metering is the most efficient
system. It makes sense to take this approach with PM
scheduling. If there is some type of meter on some piece
of equipment, that meter
can be used to set PM intervals. If the operation is
running 24/7, important PM activities may come due in a
period of 20 days instead of 30. Conversely, if orders
are down and production is running slowly, maintenance
events may be able to wait 45 days. This approach is
especially useful in scheduling seasonal equipment or
any machinery that is operated intermittently.
This method is not limited to hour
meters. It can be used with almost anything that can be
counted, like the number of boxes that are packed out at
the end of the assembly line, the number of parts, or
the number of cycles or strokes the machine makes. One
meter, at the end of an assembly line, for example, can
be used to schedule the maintenance of a whole group of
related equipment.
Regardless of the method used,
determine the capabilities of the EAM software before
making a decision. The scheduling module can be used to
look into the future to make sure that everything comes
out together.
Schedule different maintenance
activities to occur in the same downtime period. To
bring PM activities together into the same downtime
period, identify when actions are coming due, ensure
that schedules are synchronized, and audit procedures to
make sure each action is accomplished.
Start by identifying when actions
are coming due. Look further into the future—perhaps a
calendar quarter, but at least a month. As previously
mentioned, if the annual PM is also going to be due
within the next couple of weeks, consider scheduling the
annual event for the same time the monthly and quarterly
events are scheduled.
Communicate the needed downtime to
those responsible for operating the equipment so they
will not have people idle while the machinery is out of
service. Plan ahead and arrange to have all necessary
parts, permits, tools, and labor available before the
equipment is to be taken out of service.
Make sure schedules stay
synchronized, whether using “since last completed,”
“since last scheduled,” or a metered system. If they are
out of sync, adjust scheduled events to put the entire
system back into synchronization.
Finally, audit procedures to make
sure they are accomplished as scheduled. Compare
estimated labor times to actual times, and update all
estimates. Examine actual parts use and correct the
procedures to call for the right parts in the correct
quantities. Check actual downtime against estimated
downtime so that the new data will help to estimate
production downtimes in the future. Also, be sure to
solicit feedback from the people who actually have their
hands on the equipment, then update the PM procedures
using what is learned.
Once a system is in place, never
stop looking for ways to improve or modify it. Smart
Scheduling involves a little more administrative work,
but it is well worth the effort.
Contact us to learn more about Smart Scheduling and
other techniques for maximizing maintenance effectiveness.
Leland Parker is a senior consultant for DPSI.
This article was originally published in Maintenance
Technology magazine.
 |